December 8, 2017

Site Activities Week of December 11

During the week of December 11, 2017, you will see the following activities: Continued material and equipment deliveries. Begin installation of the ERH electrodes.  Drilling activities […]
December 7, 2017

Site Activities Week of December 4

During the week of December 4, 2017, you will see the following activities: Continued material and equipment deliveries, including a second power control unit, treatment system […]
October 26, 2017

EPA Public Meeting Announcement

EPA will sponsor a public meeting Thursday, November 30, 2017, at the Skyland Fire Department located at 9 Miller Road in Asheville. The meeting will begin […]
October 24, 2017

Preliminary ERH Work to Begin