Site Activities Week of December 4
December 7, 2017
Site Activities Week of December 18 and December 25
December 18, 2017

Site Activities Week of December 11

During the week of December 11, 2017, you will see the following activities:

  • Continued material and equipment deliveries.
  • Begin installation of the ERH electrodes.  Drilling activities at the site will increase and additional drill rigs will be operating at the site to install the ERH electrodes. Site personnel will begin air  monitoring near the drill rigs and waste containers using portable detectors.
  • The interior fence will be completed.
  • There will be more vehicles entering and leaving the site.

Site Safety:

Please be aware that this is an active and secured site.  Thank you for respecting the safety boundaries and please do not enter the site for any reason.

Additional Information:

If you have any questions regarding site activities, please see the contact section of this website.