Site Photo
Site Update – February 21, 2020
February 21, 2020
Site Photo
Site Update – March 6, 2020
March 6, 2020

Site Update – February 28, 2020

Site Photo

Site Update – February 28, 2020:

During the week of February 24, 2020, CTS continued the In-Situ Chemical Injection (ISCO) treatment at the completed injection well casing locations. Potassium permanganate, used to break down contaminants into harmless compounds, was injected or emplaced at 9 of the 76 locations for a total of 71 completed locations. Site work was restricted due to poor weather. Installation of emplacements will continue next week.

Site Safety:

Please be aware that this is an active and secured site.  Thank you for respecting the safety boundaries and please do not enter the site for any reason.

Additional Information:

If you have any questions regarding site activities, please see the contact section of this website.