Site Photo
Site Update – February 28, 2020
February 28, 2020
Site Photo
Site Update – March 20, 2020
March 20, 2020

Site Update – March 6, 2020

Site Photo

Site Update – March 6, 2020:

During the week of March 2, 2020, CTS finished the active injection phase of the In-Situ Chemical Injection (ISCO) treatment at the Site. Potassium permanganate, used to break down contaminants into harmless compounds, was injected or emplaced at the remainder of the 76 planned locations. The contractors performing this work will remove equipment and material from the Site over the next week.

Site Safety:

Please be aware that this is an active and secured site.  Thank you for respecting the safety boundaries and please do not enter the site for any reason.

Additional Information:

If you have any questions regarding site activities, please see the contact section of this website.