Site Photo
Site Update – December 13, 2019
December 13, 2019
Site Photo
Site Update – January 17, 2020
January 17, 2020

Site Update – January 10, 2020

Site Photo

Site Update – January 10, 2020:

During the week of January 6, 2020, CTS continued the In-Situ Chemical Injection (ISCO) treatment at the completed injection well casing locations. Potassium permanganate, used to break down contaminants into harmless compounds, was injected or emplaced at 7 of the 76 locations for a total of 15 completed locations. Installation of emplacements will continue next week.

Installation of the 76 injection well casings was completed this week.

Site Safety:

Please be aware that this is an active and secured site.  Thank you for respecting the safety boundaries and please do not enter the site for any reason.

Additional Information:

If you have any questions regarding site activities, please see the contact section of this website.