Schedule

 

  • Electrical Resistance Heating
    • 10/17 thru 11/17:  Site Prep & Equipment
    • 12/17 thru 02/18:  Install Electrodes/Vapor
      Wells, Temp Probes & Monitoring Wells
    • 02/18 thru 05/18:  Connect system
      components and test system
    • 05/18 thru 10/18:  Subsurface Heating
    • 11/18 thru 12/18:  Shutdown & Removal
  • In-Situ Chemical Oxidation
    • 12/17 thru 02/18:  Install Wells/Inject Oxidant
    • 02/18 thru 11/18:  Perform Treatability Study
    • 11/18 thru 03/19:  Design & Procure Contractor
    • 04/19:  Start ISCO Full-Scale