ERH drilling activities (185 of 227 planned electrodes installed to date) will be suspended pending relocation of the power supply line.

During the week of March 5, 2018, you will see the following activities:

  • Continued material and equipment deliveries;
  • Delivery and placement of major ERH treatment system components;
  • Relocation of the power supply line (new power poles and lines). One of the three new power poles will be installed in the DOT right-of-way outside the fence along Mills Gap Road. There will be some temporary traffic control during this installation; and
  • Construction of the ERH system components on the surface of the site.

 

Site Safety:

Please be aware that this is an active and secured site.  Thank you for respecting the safety boundaries and please do not enter the site for any reason.

Additional Information:

If you have any questions regarding site activities, please see the contact section of this website.